Example report · fictional documents
What a decision report looks like
Three fictional roofing proposals, one framework and one snapshot. Every number below comes from the sample documents, and every status can be traced to a quoted excerpt.
Contractor A
$15,400
quoted $12,500
Disposal and flashing excluded, permits unaddressed
Contractor B
$14,850
quoted $13,850
Decking allowance unresolved
Contractor C
$15,200
quoted $15,200
Broadest documented scope
Fictional roofing example · not a real quote
Framework roofing v1.0 · 14 canonical items
True cost · this scenario
Quoted price plus modeled extras
$15,400
quoted $12,500
$14,850
quoted $13,850
$15,200
quoted $15,200
14 squares
15 squares
15 squares
Not included
2 dumpsters
3 dumpsters
Not included
Step and counter
All locations
8 sheets at $95
Allowance referenced, price not stated
12 sheets at $110
Not addressed
Included
Included
40% deposit
30 / 40 / 30
25 / 50 / 25
2 years
5 years
10 years
25 years
30 years
50 years
Contractor A
$15,400
quoted $12,500
Modeled with $800 disposal, $1,200 flashing and $900 permits.
Removal of existing roof
14 squares
Haul-away and disposal
Not included
Flashing
Not included
Decking allowance
8 sheets at $95
Permits and inspections
Not addressed
Payment schedule
40% deposit
Workmanship warranty
2 years
Material warranty
25 years
Lowest modeled cost in this scenario is $14,850. It is not a recommendation: Contractor B still has an unresolved decking expense. Every modeled extra is an assumption you can change.
These are fictional documents created for demonstration. The modeled totals use fictional assumptions: A includes $800 disposal, $1,200 flashing and $900 permits; B includes $1,000 decking, still unresolved; C models no extras. None of these are guaranteed prices.
Sections in a full report
Irrelevant sections are omitted rather than left empty. Selectable text, repeated headers and page numbers, no clipped tables.
Cover and snapshot
Project, framework version, snapshot date and the documents included.
Executive summary
What differs, what is unresolved and what the decision turns on.
Investment
Quoted prices beside modeled totals, with every assumption listed.
Scope matrix
Canonical items against providers, with status and citation tags.
Specifications and exclusions
Materials as written, and exclusions quoted verbatim.
Warranty, payment and schedule
Terms side by side, not summarized into a score.
Findings
Headline, explanation, materiality, consequence and next action.
Cost scenarios
Each scenario separately, never blended into one number.
Clarification questions
Provider-specific, editable, linked to the finding that prompted them.
Revisions and decision record
What changed, what you chose and the rationale you wrote.
Methodology and evidence appendix
How items were normalized, and every excerpt with its locator.
Report templates
Detailed comparison
Full scope matrix, specifications, exclusions, terms, findings, cost scenarios and evidence appendix.
Executive brief
The decision summary, modeled investment and the findings that change the decision.
Clarification packet
Provider-specific questions with the evidence that prompted each one.
Revision report
What changed between two versions of the same provider's quote.
Decision record
The chosen provider, priorities, rationale, unresolved conditions and the snapshot relied on.